Monday, December 21, 2009

Top level Slab completed

Stairway to heaven, well not quite maybe to main bathroom, bedroom2 and garage then. The Roof trusses also arrived today.

Sunday, December 20, 2009

One level poured, one to go






The Concrete has been poured on the bottom level and the top level reinforcements are complete and ready for the top concrete pour.

Also, the timber frames have arrived, look like they will be getting a little bit of sun and rain during the Xmas break.

Wednesday, December 16, 2009

Hmmm, plenty of wine coolers





I wonder if the polar caps do melt and the coast went under water if our house will float with all these foam boxes under it? lol

Ready for the concrete trucks to arrive.

Sunday, December 13, 2009

Block cut, ground plumbing completed


The block has been cut, the base plumbing, (sewerage and storm water) completed and the electricity trench has been dug. The site has been prepared with the split level (garage, bedroom 2 and bathroom on the top level and the rest of the house on the bottom level).

Wow, where did the slope come from? I thought we bought a level block, oops.

Saturday, December 5, 2009

We finally have lift off. YAY!


Well, its a start the sign and porta-loo have arrived.